Return To Testing Home

Project Report

Review entire document, or click a section for review:

                

1.0                Introduction

1.1                Background
1.2                Purpose
1.3                Deliverables

2.0                Project information

2.1                Technical Review
2.2                Environmental Review
2.1                Discussion of Technology Application
2.2                Test Results Discussion
·        Range of Results
·        Open System Consideration
·        Design Resources

3.0                Conclusions

4.0                Recommendations

5.0                Disclaimer of Warranties and Limitation of Liabilities                                                                          
1.0  INTRODUCTION
      1.1     Background  

According to the EPA, geothermal heat pumps are the most energy-efficient, environmentally clean, and cost-effective space conditioning system available.

In a report prepared for the DOE, the Arthur D. Little Company said, "The use of geoexchange systems (geothermal heat pumps) results in increased electric load, improved (utility) asset optimization through higher annual load factors, and slower peak load growth".

 

TVA has been heavily promoting the use of geothermal heat pumps in schools and other commercial buildings since 1995.  The Customer Services and Marketing (CS&M) and the Public Power Institute (PPI) groups working together have promoted the technology and facilitated market transformation using an integrated approach.  Prior to TVA’s effort there was essentially no use of geothermal heat pumps in the commercial market. 

 

A majority of the applications have been in schools and use vertical closed-loop ground heat exchangers for the geothermal component. 

 

1.2     Purpose

 

Much work has been done in developing software and design procedures to properly size the vertical ground heat exchanger based on building loads, the thermal conductivity of the earth and the grouting/backfill methods used to install the pipe.  One important aspect of system design is determining the thermal conductivity (TC) of the earth.  This study documents the TC testing done in the Tennessee Valley and overlays the sites on a geology map in order to assist the design engineer in the preliminary system design.

 

 

1.3     Deliverables

 

The final report is the project deliverable.  The project report includes TC test results for 89 sites throughout the Tennessee Valley overlaid on a geology map.  The drill logs and TC test reports as available are included in the data contained on the attached CD ROM.


 

 

2.0  PROJECT INFORMATION

 

2.1     Technical Review

 

The American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) has sponsored research on the best practices associated with performing TC tests.[1]  The ASHRAE recommendations were for test durations of 36 to 48 hours.  The tests performed in this report range in duration from 7 hours to 49 hours.  The ASHRAE work also defines other recommended test parameters.  It should be noted that some of these tests were conducted prior to the ASHRAE research project. 

 

It is beyond the scope of this report to interpret the accuracy and/or validity of the tests procedures used by the different TC testing contractors.

 

2.2     Environmental Review

 

This project was a paper study of pre-existing TC testing.  No new test holes were drilled as part of the project.

 

Overall, the application of geothermal heat pumps should have a positive environmental effect.  According to the EPA, geothermal heat pumps are the most energy-efficient, environmentally clean, and cost-effective space conditioning system available.  In a report prepared for the DOE, the Arthur D. Little Company said, "The use of geoexchange systems (geothermal heat pumps) results in increased electric load, improved (utility) asset optimization through higher annual load factors, and slower peak load growth".

 

One concern with the installation of vertical ground heat exchangers is the protection of groundwater.  It is necessary to prevent the injection of contaminated surface waters into clean aquifers, and to prevent the cross-contamination of aquifers.  The Geothermal Heat Pump Consortium (GHPC) funded a multi-disciplined task force headed by the National Ground Water Association (NGWA) to address the requirements for the installation of vertical ground heat exchangers (to provide good thermal performance and protect the groundwater.)   The product of the task force was the NGWA printing of Guidelines for the Construction of Vertical Boreholes for Closed Loop Heat Pump Systems.  This document is available from the NGWA and represents the industry’s consensus of the best practices for installation of vertical ground heat exchangers.[2]  TVA staff participated in both the regional and national workshops in the development of the document.


 

2.3     Discussion of Technology Application

 

Determining the TC of the earth is one of the important design considerations in optimizing the design of the vertical ground heat exchanger.  The design procedure also requires an accurate load calculation with various data inputs depending on the analysis software being used.

 

Oversized ground heat exchangers perform well thermally, but run up the system first costs.  Undersized systems are cheaper to install, but suffer from extreme loop temperatures which make the systems less efficient, reduce the heating/cooling capacity, and in extreme cases cause the heat pump units to trip out on head pressure which means they can not meet the heating or cooling loads.  This is most common during the cooling cycle as commercial buildings tend to be internally load dominated, and the heat rejection to the ground loop must include both the building load and the heat of compression.

 

2.4     Test Results Discussion

 

Range of Results

TC test results conducted in the Valley ranged from a 1.03 to 2.63.  Of the 89 TC Tests included, the mean TC value was 1.63 and the median was 1.60.  There were several instances where it appeared that improper backfill resulted in a lower than expected TC value.  An example is site ST-17 where two test holes were completed in similar drilling conditions.  One test hole performed at 1.90 where a second test  hole was at 1.1.  The higher TC number was used in the reporting.  Both holes were backfilled with cuttings.  It is most likely that the lower hole had some bridging during the backfill where some of the loop was not in good contact with the earth.  This illustrates the concern of proper backfill for good thermal performance.

 

Generally the lower numbers were characterized as mostly clay.  Medium numbers were generally some soil with various limestone mixtures.  The higher numbers were typically a mix of limestone and shale for most of the depth.   The lowest TC value of 1.03 was in Paducah, KY where the drill log revealed a mix of sand and clay.  There was only 1 foot of rock encountered in the entire 310 foot borehole.  The highest TC value of 2.63 occurred in West Knoxville where the drill log indicated clay and gravel for the first 53 feet, with the remainder of the 300 foot bore hole being limestone.  Moving ground water may have contributed to the high TC value at this site.

 

Open System Considerations

In some cases a significant amount of groundwater was encountered during the test drilling.  The option of using an open system should be considered if an adequate groundwater resource is found.  Open systems have far lower first costs, however they typically have higher maintenance costs.  They also have the risk associated with the well running dry.  Proper disposal of water and the necessary permitting must be considered.  One good application is to use the water for lawn and grounds watering.  The relative advantages and disadvantages of using open systems can be discussed with the owner/operators if a large enough groundwater resource is found during the test boreholes.  If an open system is being considered, it may be more appropriate to perform a draw down test than a TC test. 

 

Design Resources

Design of both open and closed systems is discussed in detail in the ASHRAE publication Ground-Source Heat Pumps – Design of Geothermal Systems for Commercial and Institutional Buildings – Kavanaugh and Rafferty.[3]

 

An additional reference entitled Geology and Drilling Methods for Ground-Source Heat Pump Installations:  An Introduction for Engineers was developed as a joint effort of ASHRAE, the GHPC and TVA.  It is available through ASHRAE.3  The document was written by Dr. Harvey Sachs, former technical director of the GHPC and reviewed by ASHRAE’s Geothermal Utilization Technical Committee.  It is meant to provide good background information on drilling and geology as it relates to geothermal heat pumps.

 

 

3.0     CONCLUSIONS

 

The need to determine the earth’s TC in the optimum design of large vertical ground heat exchangers has been established by the industry.  The thermal conductivity mapping data will help the design engineer with at least a good cut at conceptual design and budget estimates.  For large projects, or sites with limited area it may still be best to perform drilling tests and TC tests.   Drillers are reluctant to give fixed cost prices without test bores.  Some may still want to add casing clauses.  If forced to bid fixed costs without a test borehole, drillers will usually increase the price to cover the unexpected.

 

The design engineer must ultimately decide on whether to require a test borehole and TC test.  As designers gain experience, they may be more comfortable in just doing a test bore and estimating the TC.  For smaller systems it may be acceptable to design around an estimated TC and verify the performance when the drilling starts (by reviewing drill logs and/or requiring a TC test.)  For larger the systems there is a greater need to accurately determine the TC.  As the geothermal industry matures, this should be a routine part of the design process.  As designers gain experience in systems in a specific geographic area, they may be able to accurately estimate TC.  However if the engineer handles the design by estimating a low TC, and increases the ground heat exchanger size accordingly, it could unnecessarily raise the owner’s cost.   In that case the owner would be much better off to have a test borehole and TC test done for every large job.


 

4.0     RECOMMENDATIONS

 

(A)    Continue to promote geothermal heat pumps as a high performance all-electric heating and cooling system.

(B)     Encourage design professionals to review available information such as well drilling records, geology maps, and this report when determining feasibility of potential geothermal heat pump sites.

(C)    Encourage design professionals to use TC tests as part of the design process for large geothermal jobs.

(D)    Encourage that TC tests be performed according to the ASHRAE recommendations.

(E)     Keep accurate records of future TC tests for future references.

(F)     Include GPS coordinates of any future TC sites.

(G)    Include a copy of the drill log in the TC report.

(H)    Investigate the possibility of using an open system if a significant groundwater resource is found during test borehole drilling.


 

 

5.0     DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES

 

THIS DOCUMENT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS AN ACCOUNT OF WORK SPONSORED OR COSPONSORED BY THE TENNESSEE VALLEY AUTHORITY (TVA).  NEITHER TVA, ANY DISTRIBUTOR OF TVA POWER, ANY COSPONSOR, THE ORGANIZATION(S) BELOW, NOR ANY PERSON ACTING ON BEHALF OF THEM:

 

(A)    MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER , EXPRESS OR IMPLIED, (I) WITH RESPECT TO THE USE OF ANY INFORMATION , APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT, INCLUDING MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE, OR (II)  THAT SUCH USE DOES NOT INFRINGE ON OR INTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY’S INTELLECTURAL PROPERTY, OR (III)  THAT THIS DOCUMENT IS SUITABLE TO ANY PARTICULAR USER’S CIRCUMSTANCE;  OR

(B)     ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER (INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF TVA OR ANY TVA REPRESENTATIVE HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOUR SELECTION OR USE OFTHIS DOCUMENT OR ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT.

 

ORGANIZATION(S) THAT PREPARED THIS DOCUMENT

 

TVA Pubic Power Institute

 

THE FOLLOWING SUB-CONTRACTORS PERFORMED THERMAL CONDUCTIVITY TESTS INCLUDED IN THIS REPORT:

 

(A)    Adams-Brown Services, Inc.

(B)     Earth Energy Engineering, Inc/Ewbank and Associates

(C)    Georgia Geothermal, LLC/Ewbank and Associates

(D)    Geothermal Resource Technologies, Inc.

(E)     Ted Wynne Engineering Contractors, Inc.

 

 

 

 



[1] ASHRAE 1118-TRP “Methods for Determining Soil and Rock Formation Thermal Properties from Field Tests”

[2] National Ground Water Association, 601 Dempsey Road, Westerville, Ohio 43081-8978 Phone (614) 898-7786

[3] The American Society of Heating, Refrigerating, and Air-Conditioning Engineers, 1791 Tullie Circle, N.E. Atlanta, GA 30329.  Phone (404) 636-8400.