The Tennessee Valley Authority is working with the Environmental Protection Agency to recover the site of the Kingston Fossil Plant ash spill. As part of that process, important site documents have been placed in the Administrative Record and are available for public review. The Administrative Record includes documents that form the basis for the selection of the methods TVA is using to remove ash from the river and area east of Dike 2. Documents in the Administrative Record may include, but are not limited to, inspection reports, test results, the Action Memorandum, and work plans. All interested persons are encouraged to review the documents.
These same documents are available on computer disk at the
following location:
TVA conducts public comment periods to solicit public input on important site documents and the site recovery process. To find out what public comment periods are in process and how to participate, please click here.
|
|
|
|
|
| Nbr |
Date |
Author Agency |
Title |
Pages |
NTC1 |
06/10/2009 |
TVA |
Test Embankment Program |
6 |
| NTC2 |
10/16/2009 |
TVA |
EE/CA Work Plan |
136 |
| NTC3 |
1/19/2010 |
TVA |
Engineering Evaluation/Cost Analysis (EE/CA) |
Various |
| NTC4 |
1/22/2010 |
TVA |
EECA Work Plan Responsiveness Summary |
36 |
| NTC5 |
5/18/2010 |
TVA |
Action Memorandum and Responsiveness Summary to the EE/CA |
107 |
| NTC6 |
5/21/2010 |
TVA |
Transmittal Cover for Regulatory Submittal - Deep Soil Mixing Field Demonstration Work Plan, Revision 4 |
17 |
| NTC7 |
6/3/2010 |
TVA |
Approved Final NTCRA for the River System Sampling and Analysis Plan |
258 |
| NTC8 |
6/3/2010 |
TVA |
Transmittal Cover for Regulatory Submittal - Ash Leaching Test Plan |
12 |
| NTC9 |
7/22/2010 |
TVA |
Memo to Craig Zeller re NTC water |
1 |
| NTC10 |
7/26/2010 |
TVA |
Surface Water Monitoring Plan
for the
Emory, Clinch, and Tennessee Rivers |
47 |
| NTC11 |
7/26/2010 |
TVA |
Site Dust Control and Air Monitoring Plan |
35 |
| NTC12 |
8/10/2010 |
TVA |
Central Area Re-contouring Work Plan Rev 5 |
10 |
| NTC13 |
8/23/2010 |
TVA |
Non-Time-Critical Removal Action Work Plan for the Embayment Dredge Cell |
57 |
| NTC14 |
9/10/2010 |
TVA |
Interim Dredge Cell Ash Stacking and Instrumentation Design Package |
40 |
| NTC15 |
9/20/2010 |
TVA |
Non-Time-Critical Removal Action for the Swan Pond Embayment Ash Removal Design Package (Revison 3 Drawings Only) |
30 |
| NTC16 |
09/20/2010 |
TVA |
Site Storm Water Management Plan |
49 |
| NTC17 |
12/14/2010 |
TVA |
Gupton Farm Road Removal Work Plan |
6 |
| NTC18 |
01/06/2011 |
TVA |
Non-Time-Critical Removal Action Field Change Notice For Lime Addition |
5 |
| NTC19 |
03/21/2011 |
TVA |
Non-Time Critical Work Plan for Ash Stablization Demonstration in Support of Dredge Cell Ash Stacking |
5 |
| NTC20 |
04/05/2011 |
TVA |
Pine Ridge Borrow Study Work Plan |
6 |
| NTC21 |
04/11/2011 |
TVA |
Non-Time Critical Work Plan for the Perimeter Stabilization Field Demonstration in Support of Dredge Document no. EPA-AO-034 |
8 |
| NTC 22 |
04/25/2011 |
TVA |
Gupton Borrow Area Work Plan |
7 |
| NTC 23 |
05/17/2011 |
|
North Embayment Non-Time Critical Concurrence |
12 |
| NTC 24 |
07/05/2011 |
TVA |
North Embayment Non-Time Critical Concurrence Grids 4-E and 3-J |
18 |
| NTC 25 |
07/07/2011 |
TVA |
Non-Time Critical Lateral Expansion (Cell 4) Ash Stacking 90% Review |
253 |
| NTC 26 |
07/13/2011 |
TVA |
Non-Time Critical Site Storm Water Management Plan, Revision 2 |
44 |
| NTC 27 |
08/02/2011 |
TVA |
Non-Time Critical Removal Action Surface Water Monitoring Plan |
35 |
| NTC 28 |
08/09/2011 |
TVA |
Non-Time-Critical Perimeter Containment North Dredge Cell (Dike C) Segment 1 Design Package and the Revised Technical Specifications and Quality Control Plan for Perimeter Wall Stabilization |
510 |
| NTC 29 |
08/22/2011 |
TVA |
Semi-Annual Performance Audits, Network Review, and Data Review of the Ambient Air Monitoring Network |
13 |
| NTC 30 |
08/22/2011 |
TVA |
Non-Time-Critical Removal Action
River System Sampling and Analysis Plan
Task Completion Technical Memorandum
Amphibian Sampling |
39 |
| NTC 31 |
08/22/2011 |
TVA |
Non-Time-Critical Removal Action
River System Sampling and Analysis Plan
Task Completion Technical Memorandum
Piscivorous and Herbivorous Bird Egg Sampling |
32 |
| NTC 32 |
08/22/2011 |
TVA |
Non-Time-Critical Removal Action
River System Sampling and Analysis Plan
Task Completion Technical Memorandum
Groundwater Sampling |
186 |
| NTC 33 |
08/22/2011 |
TVA |
Non-Time-Critical Removal Action
River System Sampling and Analysis Plan
Task Completion Technical Memorandum
Surface Water |
37 |
| NTC 34 |
08/22/2011 |
TVA |
Non-Time-Critical Removal Action
River System Sampling and Analysis Plan
Task Completion Technical Memorandum
Tree Swallow Sampling |
57 |
| NTC 35 |
08/22/2011 |
TVA |
Non-Time-Critical Removal Action
River System Sampling and Analysis Plan
Task Completion Technical Memorandum
Turtle Sampling |
44 |
| NTC 36 |
08/22/2011 |
TVA |
Non-Time-Critical Removal Action
River System Sampling and Analysis Plan
Task Completion Technical Memorandum
Fish Sampling |
333 |
| NTC 37 |
08/29/2011 |
TVA |
Non-Time Critical Concurrence: Area: 1-A,1-B, 1-C, 1-F, 1-G, 1-H, 2-A, 2-B, 2-D, 2-E, 2-F, 2-G, 2-H, 3-A, 3-B, 3-C, 3-D, 3-E, 3-F west of Clean Water Ditch. 3-G, 3-H, 4-B west of Clean Water Ditch, 4-C & 4-D and delineated area north of Grid 1-B |
32 |
| NTC 38 |
08/30/2011 |
TVA |
Non-Time Critical Removal Addendum for Swan Pond Embayment Ash Removal North Embayment Phase 1 Phase 2 Design Drawings |
4 |
| NTC 39 |
09/21/2011 |
TVA |
Field Change Notice-034 - Perimeter Wall Stabilization Segment 1 Sta A161+50 to Sta 179+50 |
28 |
| NTC 40 |
09/26/2011 |
TVA |
Non-Time-Critical 90% design package ash pond outlet structure |
173 pgs |
| NTC 41 |
09/27/2011 |
TVA |
Non-Time-Critical Concurrence North Embayment Grids S·N, S-M, 6-E, 6·F ,6·L and 7-E covered by the Swan Pond Road stabilization buttress. |
26 |
| NTC 42 |
11/02/2011 |
TVA |
Non-Time-Crtiical Concurrence for a portion of the North Embayment Grids 4-H, 4-J, 4-K, 4-L, 5-G, 5-F, 5-E, 5-D, 5-K, 5-L, 5-M, 6-D, 6-K, 6-L and eastern portion of 6-E |
86 |
| NTC 43 |
11/04/2011 |
TVA |
Non-Time-Critical Removal Action
River System Sampling and Analysis Plan
Task Completion Technical Memorandum
Aquatic Vegetation and Periphyton Sampling |
41 |
| NTC 44 |
11/07/2011 |
TVA |
Non-Time-Critical Removal Action
Site Dust Control and Air Monitoring Plan |
30 |
| NTC 45 |
12/12/2011 |
TVA |
Non-Time-Critical Removal Action for the River System. Supplemental Ash Leaching Test Results |
113 |
| NTC 46 |
12/12/2011 |
TVA |
Non-Time Critical Concurrence: Area: The North Embayment Grids 5-N, 5-J, 5-H, 5-A, 6-C, 6-B, 6-J, 6-H, 6-G, 7-E, 7-D, 7-C, 7-B, and 7-A. |
104 |
| NTC 47 |
12/12/2011 |
TVA |
Non-Time Critical Concurrence: Area: The North Embayment Grids 3-F, 4-A, 4-G, 5-B, and 5-C |
46 |
| NTC 48 |
12/12/2011 |
TVA |
Non-Time Critical Removal (Phase III) Action for the Swan Pond Embayment Ash Removal Design package. |
32 |
| NTC 49 |
12/12/2011 |
TVA |
Non-Time Critical Concurrence: Area: The North Embayment Grids 7-G, 7-H, 7-J, 7-K, 7-L |
37 |
| NTC 50 |
12/19/2011 |
TVA |
Perimeter Wall Stabilization (PWS) Segment 1A Test Parcel No. 11 (TP11) Non-Time Critical Completion Concurrence and Acceptance Kingston Perimeter Containment - Segment 1 (RDP-0113-E) |
5 |
| NTC 51 |
12/19/2011 |
TVA |
Perimeter Wall Stabilization (PWS) Segment 1A Test Parcel No. 13 (TP13) Non-Time Critical Completion Concurrence and Acceptance Kingston Perimeter Containment - Segment 1 (RDP-0113-E) |
5 |
| NTC 52 |
12/19/2011 |
TVA |
Perimeter Wall Stabilization (PWS) Segment 1A Test Parcel No. 9 (TP9) Non-Time Critical Completion Concurrence and Acceptance Kingston Perimeter Containment - Segment 1 (RDP-0113-E) |
5 |
| NTC 53 |
02/01/2012 |
TVA |
Perimeter Wall Stabilization Segment 1B Test Parcel No. 29 Completion Concurrence and Acceptance |
5 |
| NTC 54 |
02/02/2012 |
TVA |
Swan Pond Road (Segment 7) Perimeter Containment Design (90% Submittal) |
418 |
| NTC 55 |
02/06/2012 |
TVA |
Non-Time-Critical Removal Action Design Package North Wall Segment 8 Perimeter Containment Design 90 percent |
164 |
| NTC 56 |
03/01/2012 |
TVA |
Non-Time-Critical North and Central Dredge Cell (Cells 2 and 3) Closure |
140 |
| NTC 57 |
03/08/2012 |
TVA |
Approved concurrence for the Perimeter Wall Stabilization, Test Parcel 31 for Segment 1A |
5 |
| NTC 58 |
03/21/2012 |
TVA |
Approved concurrence for Test Parcel 10 of Segment 1 of PWS |
5 |
| NTC 59 |
03/21/2012 |
TVA |
Approved concurrence for Test Parcel 31 of Segment 1 of PWS |
5 |
| NTC 60 |
04/30/2012 |
TVA |
Non-Time-Critical Removal Action
Surface Water Monitoring Plan |
37 |
| NTC 61 |
05/8/2012 |
TVA |
Perimeter Wall Stabilization (PWS) Segment 1 Test Parcel No. 20 (TP20) Completion Concurrence and Acceptance Kingston Perimeter Containment – Segment 1 (RDP-0113-E) |
5 |
| NTC 62 |
05/8/2012 |
TVA |
Non-Time-Critical Removal Action for the River System Sampling and Analysis Plan (SAP) Supplement A |
94 |
| NTC 63 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Surface Water |
35 |
| NTC 64 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Amphibian Sampling |
39 |
| NTC 65 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Piscivorous and Herbivorous Bird Egg Sampling |
32 |
| NTC 66 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Groundwater Sampling |
187 |
| NTC 67 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Tree Swallow Sampling |
57 |
| NTC 68 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Turtle Sampling |
44 |
| NTC 69 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Fish Sampling |
383 |
| NTC 70 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Raccoon Sampling |
48 |
| NTC 71 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Ash Deposits, Submerged Sediment, and Seasonally-Exposed Sediment |
194 |
| NTC 72 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Aquatic Vegetation and Periphyton Sampling |
41 |
| NTC 73 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Sediment Bioassay and Porewater |
86 |
| NTC 74 |
05/9/2012 |
TVA |
River System Sampling and Analysis Plan Task Completion Technical Memorandum Benthic Invertebrate Sampling |
103 |
| NTC 75 |
06/11/201 |
TVA |
Approved acceptance and concurrence for TP 801 of Segment 8 of the PWS |
5 |
| NTC 76 |
06/11/201 |
TVA |
Approved acceptance and concurrence for TP 802 of Segment 8 of the PWS |
5 |
| NTC 77 |
06/11/2012 |
TVA |
Approved Concurrence and Acceptance for TP 803 of Segment 8 of the PWS |
5 |
| NTC 78 |
06/11/2012 |
TVA |
Approved Concurrence and Acceptance for TP 804 of Segment 8 of the PWS |
5 |
| NTC 79 |
06/19/2012 |
TVA |
Approved Transmittal Cover for Regulatory Submittal for Kingston Fossil Plant - NTC RDP Perimeter Containment Lateral Expansion- Segment 2 |
170 |
| NTC 80 |
06/21/2012 |
TVA |
Approved Transmittal Cover for Regulatory Submittal for Kingston Fossil Plant - Sluice Trench Outlet Piping |
29 |
| NTC 81 |
07/23/2012 |
TVA |
Approved Lateral Expansion Closure design package |
160 |
| NTC 82 |
08/06/2012 |
TVA |
Approved - Transmittal Cover for Regulatory Submittal for KRP - NTC 90 % Design for Ash Pond Ash Stacking |
53 |
| NTC 83 |
08/10/2012 |
|
River System Engineering Evaluation/Cost Analysis |
Various |
| NTC 84 |
08/20/2012 |
TVA |
Storm Water Pollution Prevention Plan – North Borrow Area |
59 |
| NTC 85 |
08/27/2012 |
TVA |
Field Change Notice for Cold Joint Definition |
254 |
| NTC 86 |
08/27/2012 |
TVA |
General Mitigation Plan for
Cold Joints, Defects and
Other Nonconforming Soil-
Cement Walls |
34 |
| NTC 87 |
11/07/2012 |
TVA |
River System Action Memorandum |
55 |
| NTC 88 |
11/20/2012 |
TVA |
Approved plan for Entrance Restoration Work Plan |
5 |
| NTC 89 |
12/07/2012 |
TVA |
90 percent Design for Segments 3 and 4 Perimeter Containment - Approved |
1917 |
| NTC 90 |
12/10/2012 |
TVA |
Approved concurrence for Grids 9-A, 10-B and Portions of Grids 9-B and 10-C in the Middle Embayment |
28 |
| NTC 91 |
12/17/2012 |
TVA |
Approved Embayment Restoration Grading and Weirs |
17 |
| NTC 92 |
12/19/2012 |
TVA |
Approved - Non-Time-Critical Concurrence Middle Embayment Grids 8B-D, 9 B-D and 10 C – E |
22 |
| NTC 93 |
12/20/2012 |
TVA |
Site Dust Control and Air Monitoring Plan |
31 |
| NTC 94 |
03/07/2013 |
TVA |
Approved-Revised Surface Water Monitoring Plan (February 2013) |
23 |
| NTC 95 |
03/14/2013 |
TVA |
Removal Action Work Plan
for the River System |
37 |