July 2009

Making the most of rainfall

In three years of drought, lead engineers Nikki Berger and John Hoover and their River Operations colleagues have been working hard to move enough water through the Tennessee River system to provide adequate depth for barges, cooling water for nuclear and fossil plants, water quality, hydro generation and water supplies and recreation for the region.

photo

Nikki Berger was on duty when the spilling of Norris Dam began, and John Hoover gave the order to stop the spilling four days later.

The drought began in 2006 when the Tennessee Valley had its 27th-lowest total rainfall in 120 years of recordkeeping. In 2007, it hit bottom, with the lowest total rainfall on record, followed by the 15th-lowest annual total in 2008. The lack of hydropower those years cost TVA $1.5 billion for replacement power.

This spring, when it did rain, it poured. But conditions have become dry again, and runoff – the portion of the rainfall that actually makes it into the reservoir system — is only about 78 percent of normal in the eastern part of the Valley.

“We had three years with the water table receding and wells going dry,” says Hoover. “The dry, starved ground is still soaking up lots of that rainfall.”

photo
“Rainfall is still below normal for the year, and signs are pointing to below-normal rainfall for the next few months,” says Mike Eiffe, program manager in Water Supply.

In early May, with heavy rains in northeast Tennessee, the River Operations team went to work to meet another basic purpose of the river system: flood control. The rains raised the level of Norris Reservoir to 1,024 feet, about four feet above the target summer level.

To bring the level back down, the flow through the turbines at Norris Dam was increased to the maximum 9,500 cubic feet per second around the clock. But even that could not move water out of the reservoir fast enough to keep up with the water surging in.

On Monday, May 11, Berger gave the order for technicians at Norris Dam to open the three spillway gates – the first time TVA had opened the gates for flood control since 2003.

photo

In the River Forecasting Center, Manager Susan Jacks talks with newly recruited civil engineer James Everett.

Those rains helped bring the total rainfall so far this fiscal year to 94 percent of normal for the entire Valley. Hydropower generation is about 82 percent of normal, up from 50 percent in 2008, 70 percent in 2007 and 73 percent in 2006.

Still, says senior Vice President for River Operations Janet Herrin, “We’re not out of the woods.” In fact, in recent weeks the eastern portion of the Valley has received less-than-normal rainfall, and forecasts call for below-normal precipitation for the next few months.

Without sustained inflows into the system, some water in the tributary reservoirs will have to be used keep up minimum flows through the system, and that will affect reservoir levels. It will also affect TVA’s less costly source of power — hydro generation.

So, will the Valley get back to normal rainfall this summer?

“That’s the million-dollar question,” says Hoover. “In the end, we’ll react to whatever Mother Nature provides us, to the best of our ability.”

Recreation abounds

During the week of spilling, Oak Ridge Rowing Association coach Allen Eubanks watched the fast-moving water and shoreline debris — sticks, logs and trees — put stress on and even snap the underwater wires holding lane buoys in place at the Melton Lake Rowing Venue, some 15 miles downstream from Norris Dam.

The current was strong enough that Eubanks couldn’t keep a launch in place long enough to fix the broken wires. Once the spilling stopped, Eubanks and his team of volunteers made repairs — just in time for that weekend’s collegiate regatta, the Aramark South/central Sprints, which attracted hundreds of rowers from as far away as Minnesota, Pennsylvania and Texas.

The Melton Hill reservoir is regarded as one of the best rowing venues in the nation, in part because of River Operations’ cooperation in moderating water flow, when feasible, during big events.

“We coordinate with them,” says River Operations’ John Hoover. “We know when the rowing events are and try to send down the minimum amount of water dictated by our flow requirements.”

Each year, the site hosts a dozen or so major regattas, as well as spring training for 32 college teams, providing significant revenue for area hotels and restaurants.

photo

A women’s 8 takes a break after racing at the Melton Lake Rowing Venue in Oak Ridge, Tenn.