|
Regenesys
Electricity is a
tricky commodity. Unlike soybeans or corn, it cant be stored for
later use. But a new TVA project could change all that.
This past October
TVA began building the nations first large-scale, flow-battery power
storage facility in Columbus, Mississippi. The plant will use the Regenesys
technology to store electricity during off-peak periods and retrieve it
for use when the need for power increases. Located east of Columbia Air
Force Base, the facility is being designed to store up to 120 megawatt-hours
of energy. Once fully charged, it will be capable of providing power to
some 7,500 homes for 10 hours or more.
The Regenesys plant
will be similar to the Raccoon Mountain Pumped Storage Plant in its ability
to store power. However, the Regenesys chemical process is very different
from that used at Raccoon Mountain, which pumps water from the Tennessee
River up to a mountaintop lake when power demand is low, then releases
the water through turbines at times of high power demand.
During periods of
low demand for electricity, a reversible electrochemical reaction between
two salt solutions charges the Regenesys system, using power generated
at other plants. The process reverses itself to transmit the stored energy
when demand for power rises.
This innovative
energy-storage plant is designed to improve power reliability and customer
service, have limited environmental impact, and contribute to economic
growth for consumers in Mississippi and throughout the Tennessee Valley,
says TVA Chairman Glenn McCullough, Jr. The project is another way
in which TVA continues to set the pace for energy production and demonstrate
its role as a national leader in the use of cutting-edge, 21st-century
technologies.
To help meet the
growing demand for electricity, TVA’s Public Power Institute has been
working with the British company Regenesys Technologies to introduce the
new power storage system in the U.S. The project, approved by the TVA
Board in November 2000, will cost in excess of $25 million and will create
about 60 jobs during construction, which will last about two years. Construction
began in October 2001.
The Regenesys plant
is one of a number of Public Power Institute projects that are designed
to improve the TVA power system by increasing energy supply and delivery
reliability.
Construction Highlights:


Construction is on
schedule for mechanical completion by April 2003. At that point
the delivery of Electrolytes and the Regenerative Cells or Modules is
possible.

|